Filter by category
Filter by Date
NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025
NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 20/02/2025 02:20 to 20/02/2025 03:00
Amount: -9 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124832
PPCCGT PELICAN POINT at 0400 hrs 20/02/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 21/02/2025.
The direction update is issued at 1600 hrs 19/02/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124831
TORRB2 TORRENS ISLAN at 0400 hrs 20/02/2025 to Remain synchronised and follow dispatch targets.
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 21/02/2025.
The direction update is issued at 1600 hrs 19/02/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 19 February 2025
NON-CONFORMANCE QLD1 Region Wednesday, 19 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 19/02/2025 11:55 to 19/02/2025 12:10
Amount: -18 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 19/02/2025
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 19/02/2025
A planned outage of South Morang - Dederang No.1 330kV line series capacitor in the VIC region was scheduled from 0449 hrs 04/02/2025 to 1700 hrs 31/03/2025.
The outage has been completed and South Morang - Dederang No.1 330kV line series capacitor returned to service at 1205 hrs 19/02/2025
Constraint set(s) revoked: V-SMSC
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124819
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 20/02/2025.
The direction update is issued at 1600 hrs 18/02/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124767
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 20/02/2025.
The direction update is issued at 1600 hrs 18/02/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124769
Required actions update: Remain synchronised and follow dispatch targets at 0800 hrs 18/02/2025
The direction update is issued at 0720 hrs 18/02/2025.
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124618
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 17/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 18/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 19/02/2025.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations