Filter by category
Filter by Date
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 854 MW
The minimum capacity reserve available is 543 MW
Manager NEM Real Time Operations
[EventId:202501221405_review] Prices for interval 22-Jan-2025 14:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 22 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2025 14:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501221400_review] Prices for interval 22-Jan-2025 14:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 22 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2025 14:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501221355_review] Prices for interval 22-Jan-2025 13:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1350 hrs on 22 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2025 13:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501221350_review] Prices for interval 22-Jan-2025 13:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1345 hrs on 22 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2025 13:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501221345_review] Prices for interval 22-Jan-2025 13:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 22 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2025 13:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501221340_review] Prices for interval 22-Jan-2025 13:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 22 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2025 13:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 123546 is cancelled at 0800 hrs 22/01/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs 28/01/2025 to 1700 hrs 28/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 570 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations