123931INTER-REGIONAL TRANSFER30/01/2025 03:24:25 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 2 Leg of Directlink .

The following constraint set was invoked at 1525 hrs 30/01/2025

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
123926RESERVE NOTICE30/01/2025 02:45:47 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following period:

From 1630 hrs to 1830 hrs 03/02/2025.
The forecast capacity reserve requirement is 1130 MW.
The minimum capacity reserve available is 1022 MW.

AEMO Operations
     
123919GENERAL NOTICE30/01/2025 11:11:45 AM

NEM Local Temperature Alerts for SA, TAS, VIC from 30 Jan 2025 to 03 Feb 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Adelaide West Terrace (39+ Deg C): 2nd Feb, 3rd Feb
Clare High School (39+ Deg C): 2nd Feb, 3rd Feb
Mt Gambier Ap (39+ Deg C): 2nd Feb, 3rd Feb
Port Augusta Ap (39+ Deg C): 1st Feb, 2nd Feb, 3rd Feb

TAS
Launceston Ti Tree Bend (33+ Deg C): 2nd Feb, 3rd Feb

VIC
Melbourne Olympic Park (39+ Deg C): 3rd Feb
Mildura Ap (39+ Deg C): 1st Feb, 2nd Feb, 3rd Feb
Mortlake (39+ Deg C): 3rd Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
123917NON-CONFORMANCE30/01/2025 06:50:11 AM

NON-CONFORMANCE Region NSW1 Thursday, 30 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 30 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 30/01/2025 06:45 to 30/01/2025 06:50
Amount: -14 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123886RESERVE NOTICE29/01/2025 02:46:45 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 123813 is cancelled at 1400 hrs 29/01/2025.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
123863GENERAL NOTICE29/01/2025 01:24:31 PM

NEM Local Temperature Alerts for SA, VIC from 29 Jan 2025 to 02 Feb 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Adelaide West Terrace (39+ Deg C): 2nd Feb
Clare High School (39+ Deg C): 2nd Feb
Mt Gambier Ap (39+ Deg C): 2nd Feb
Port Augusta Ap (39+ Deg C): 1st Feb, 2nd Feb

VIC
Mildura Ap (39+ Deg C): 1st Feb, 2nd Feb
Mortlake (39+ Deg C): 2nd Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
123858INTER-REGIONAL TRANSFER29/01/2025 10:16:37 AM

Inter-regional transfer limit variation - TIPS - Para 275kV Line- SA region - 29/01/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - TIPS - Para 275kV Line - SA region - 29/01/2025

At 0930 hrs 29/01/2025 there was a short notice outage of TIPS - Para 275kV Line.

The following constraint set(s) invoked at 0930 hrs 29/01/2025
S-X_MGTI+PATI

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
123843NON-CONFORMANCE29/01/2025 08:40:11 AM

NON-CONFORMANCE Region NSW1 Wednesday, 29 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 29 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CAPBES1
Duration: 29/01/2025 08:35 to 29/01/2025 08:40
Amount: -100 MW
Constraint: NC-N_CAPBES1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123820NON-CONFORMANCE28/01/2025 06:10:14 PM

NON-CONFORMANCE Region QLD1 Tuesday, 28 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 28 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 28/01/2025 17:55 to 28/01/2025 18:10
Amount: -17 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     