Market Notices

124913NON-CONFORMANCE20/02/2025 03:45:14 AM

NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 20/02/2025 03:30 to 20/02/2025 03:45
Amount: -8 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124912NON-CONFORMANCE20/02/2025 03:00:19 AM

NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 20/02/2025 02:20 to 20/02/2025 03:00
Amount: -9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124893MARKET SYSTEMS19/02/2025 03:01:56 PM

Completed - CHG0101145 - Planned Maintenance to Norwest Internet Router

Change Number: CHG0101145

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet Router

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
124888MARKET SYSTEMS19/02/2025 01:04:49 PM

Inital - CHG0101252 - Retail Pre-Production Data refresh (CATS and EMDM)

Change Number: CHG0101252

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Retail Pre-Production Data refresh (CATS and EMDM)

Change Start Date & Time: 24/02/2025 09:00:00
Change End Date & Time: 28/02/2025 18:00:00
Outage Start Date & Time: 24/02/2025 09:00:00
Outage End Date & Time: 27/02/2025 18:00:00

Environment: Pre-Production
Participant Impact and Requirements: MSATS (preprod) between 24th Feb - 26 Feb COB, CDR (preprod) and CDP (preprod) will be unavailble between 24th Feb to 28th Feb COB

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
124879NON-CONFORMANCE19/02/2025 12:10:21 PM

NON-CONFORMANCE Region QLD1 Wednesday, 19 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 19 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 19/02/2025 11:55 to 19/02/2025 12:10
Amount: -18 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
124873MARKET SYSTEMS19/02/2025 11:47:12 AM

Inital - CHG0100546 - Production eMDM February Maintenance Release

Change Number: CHG0100546

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: MDM - Meter Data Management
Change Title: Production eMDM February Maintenance Release

Change Start Date & Time: 23/02/2025 10:00:00
Change End Date & Time: 23/02/2025 17:00:00
Outage Start Date & Time: 23/02/2025 10:00:00
Outage End Date & Time: 23/02/2025 14:00:00

Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
124774MARKET SYSTEMS17/02/2025 03:33:27 PM

Change Title: Planned System Maintenance - Declared Wholesale Gas Market (DWGM)

Change Number: CHG0100700

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Declared Wholesale Gas Market
Change Title: Planned System Maintenance - Declared Wholesale Gas Market (DWGM)
Change Start Date & Time: 18/02/2025 09:00:00
Change End Date & Time: 18/02/2025 21:00:00
Outage Start Date & Time: 18/02/2025 18:30:00
Outage End Date & Time: 18/02/2025 20:30:00
Environment: Production
Participant Impact and Requirements: DWGM market system (Webexchanger and MIBB) outage due to planned maintenance.

The following impacts are expected during the maintenance activities:
- All access to the Declared Wholesale Gas Market Production Systems will be unavailable.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned
     
124762MARKET SYSTEMS17/02/2025 11:40:07 AM

Change Title: Pre-production EMMS database refresh

hange Number: CHG0101226

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: Pre-production EMMS database refresh
Change Start Date & Time: 17/02/2025 09:00:00
Change End Date & Time: 12/03/2025 17:00:00
Outage Start Date & Time: 24/02/2025 09:00:00
Outage End Date & Time: 28/02/2025 17:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Electricity Market Management System (EMMS) and Gas Supply Hub (GSH) Pre-Production environment will be unavailable during the outage window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
124729NON-CONFORMANCE15/02/2025 03:55:18 PM

NON-CONFORMANCE Region QLD1 Saturday, 15 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 15 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 15/02/2025 15:50 to 15/02/2025 15:55
Amount: 15 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
X