124106SETTLEMENTS RESIDUE04/02/2025 03:32:57 PM

[EventId:202502041530_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 February 2025 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 4 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1530 hrs on 4 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124098SETTLEMENTS RESIDUE04/02/2025 03:07:51 PM

[EventId:202502041500_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 04 February 2025 15:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 4 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Refer to market notice: 124084

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1500 hrs on 4 February 2025.

This is an AEMO autogenerated Market Notice.
     
124091RESERVE NOTICE04/02/2025 03:01:16 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124059 has been updated at 1420 hrs 04/02/2025 to the following:

[1.] From 1530 hrs 04/02/2025 to 1630 hrs 04/02/2025.
The forecast capacity reserve requirement is 1663 MW.
The minimum capacity reserve available is 1277 MW.

[2.] From 1830 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1652 MW.
The minimum capacity reserve available is 974 MW.


Manager NEM Real Time Operations
     
124084SETTLEMENTS RESIDUE04/02/2025 02:42:10 PM

[EventId:202502041335_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 04 February 2025 13:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1335 hrs on 4 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1335 hrs on 4 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124077MARKET SYSTEMS04/02/2025 02:17:21 PM

CHG0101137 | Completed | Production | Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Change Number: CHG0101137

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Local Area Network

Change Title: Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
124069SETTLEMENTS RESIDUE04/02/2025 01:15:58 PM

[EventId:202502041300_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 04 February 2025 13:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 4 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Refer to market notice: 124064

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1300 hrs on 4 February 2025.

This is an AEMO autogenerated Market Notice.
     
124064SETTLEMENTS RESIDUE04/02/2025 11:35:33 AM

[EventId:202502041135_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 04 February 2025 11:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 4 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1135 hrs on 4 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124060INTER-REGIONAL TRANSFER04/02/2025 05:11:43 AM

Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025

At 0449 hrs 04/02/2025 there was an unplanned outage of South Morang - Dederang No.1 330kV line series capacitor.

The following constraint set(s) invoked at 0505 hrs 04/02/2025
V-SMSC

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124059RESERVE NOTICE04/02/2025 04:02:18 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124049 has been updated at 0400 hrs 04/02/2025 to the following:

[1.] From 1630 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1703 MW.
The minimum capacity reserve available is 1136 MW.