Market Notices

124034RESERVE NOTICE03/02/2025 04:54:30 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 124026 has been updated at 0445 hrs 03/02/2025 to the following:

[1.] From 1800 hrs 03/02/2025 to 1830 hrs 03/02/2025.
The forecast capacity reserve requirement is 598 MW.
The minimum capacity reserve available is 419 MW.

[2.] From 1930 hrs 03/02/2025 to 2030 hrs 03/02/2025.
The forecast capacity reserve requirement is 617 MW.
The minimum capacity reserve available is 380 MW.


Manager NEM Real Time Operations
     
124026RESERVE NOTICE03/02/2025 12:03:05 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 1800 hrs 03/02/2025 to 2000 hrs 03/02/2025.
The forecast capacity reserve requirement is 630 MW.
The minimum capacity reserve available is 384 MW.


Manager NEM Real Time Operations
     
124025RESERVE NOTICE03/02/2025 12:09:13 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:


[1.] From 1800 hrs 03/02/2025 to 1930 hrs 03/02/2025.
The forecast capacity reserve requirement is 1135 MW.
The minimum capacity reserve available is 999 MW.


Manager NEM Real Time Operations
     
124020INTER-REGIONAL TRANSFER02/02/2025 10:38:53 PM

Update - Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.

The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA

The following constraint set(s) invoked at 2230 hrs 02/02/2025
V-KIAMAL_SC_220CB

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124017INTER-REGIONAL TRANSFER02/02/2025 10:04:02 PM

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.

The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124000RESERVE NOTICE02/02/2025 02:39:02 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:

[1.] From 1600 hrs 07/02/2025 to 1800 hrs 07/02/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1160 MW.

Manager NEM Real Time Operations
     
123980INTER-REGIONAL TRANSFER01/02/2025 08:53:03 AM

Inter-regional transfer limit variation - Armidale - Tamworth No. 86 330 kV Line - NSW region - 01/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Tamworth No. 86 330 kV Line - NSW region - 01/02/2025

A planned outage of Armidale - Tamworth No. 86 330 kV Line in the NSW region was scheduled to be completed at 1030 hrs 01/02/2025

The outage has been completed by 0835 hrs 01/02/2025

Constraint set(s) invoked:
N-ARTW_86
N-DM_SVC
N-TW_SVC


This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
123962RESERVE NOTICE31/01/2025 03:03:30 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 123926 is cancelled at 1400 hrs 31/01/2025.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
123943PRICES SUBJECT TO REVIEW30/01/2025 06:42:26 PM

[EventId:202501301835_review] Prices for interval 30-Jan-2025 18:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 30 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm