Market Notices

124182MARKET INTERVENTION05/02/2025 03:58:42 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 124097


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 05/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 06/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1300 hrs 06/02/2025 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
124181POWER SYSTEM EVENTS05/02/2025 03:22:35 PM

Update - Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 03/02/2025

Refer AEMO Electricity Market Notice 124044

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will cancel the reclassification of this event as a credible contingency event.

Manager NEM Real Time Operations
     
124167PRICES SUBJECT TO REVIEW05/02/2025 01:22:24 PM

[EventId:202502051320_review] Prices for interval 05-Feb-2025 13:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124165MARKET INTERVENTION05/02/2025 01:18:56 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 124096

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 05/02/2025.

The direction update is issued at 1315 hrs 05/02/2025.

Manager NEM Real Time Operations
     
124163PRICES SUBJECT TO REVIEW05/02/2025 01:12:36 PM

[EventId:202502051315_review] Prices for interval 05-Feb-2025 13:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124162PRICES SUBJECT TO REVIEW05/02/2025 01:06:20 PM

[EventId:202502051310_review] Prices for interval 05-Feb-2025 13:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124161PRICES SUBJECT TO REVIEW05/02/2025 01:10:31 PM

[EventId:202502051305_review] Prices for interval 05-Feb-2025 13:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124159PRICES SUBJECT TO REVIEW05/02/2025 01:08:27 PM

[EventId:202502051300_review] Prices for interval 05-Feb-2025 13:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1255 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124158PRICES SUBJECT TO REVIEW05/02/2025 12:51:50 PM

[EventId:202502051255_review] Prices for interval 05-Feb-2025 12:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1250 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 12:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm