Cancellation - AEMO Intervention Event - SA region 15/03/2025
Cancellation - AEMO Intervention Event - SA region 15/03/2025
Refer to Market Notice 125670
The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 18/03/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 125709
Direction is cancelled from: 0400 hrs 18/03/2025
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125755
Direction is cancelled from: 1730 hrs 17/03/2025
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125710
The PPCCGT PELICAN POINT direction is now expected to stay in place until 1730 hrs 17/03/2025.
The direction update is issued at 1620 hrs 17/03/2025.
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125751.
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 17/03/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0800 hrs 18/03/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1600 hrs 18/03/2025.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 17/03/2025
Direction - SA region 17/03/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 17/03/2025.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Foreseeable AEMO intervention in SA region
Foreseeable AEMO intervention in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 18/03/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 17/03/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 17 March 2025
NON-CONFORMANCE QLD1 Region Monday, 17 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WARWSF1
Duration: 17/03/2025 12:05 to 17/03/2025 12:10
Amount: 16 MW
Constraint: NC-Q_WARWSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Sunday, 16 March 2025
NON-CONFORMANCE NSW1 Region Sunday, 16 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 16/03/2025 18:15 to 16/03/2025 18:20
Amount: -10 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations