STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1500 hrs to 1830 hrs 28/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 859 MW.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 123649 has been updated to the following:
[1.] From 1830 hrs 24/01/2025 to 1900 hrs 24/01/2025.
The forecast capacity reserve requirement is 854 MW.
The minimum capacity reserve available is 812 MW.
Manager NEM Real Time Operations
CHG0100610 | Production | Planned Maintenance to Brisbane Internet Router
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet Router
Change Start Date & Time: 01/02/2025 11:00:57 AEST
Change End Date & Time: 01/02/2025 13:00:57 AEST
Outage Start Date & Time: 01/02/2025 11:00:31 AEST
Outage End Date & Time: 01/02/2025 13:00:31 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 1 Hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10 for Policy Based VPN and 202.44.76.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.
B2B VPN - Up to 1 hour outage to TNSPs with B2B VPN to AEMO QLD Datacentre if VPN connection is only terminating in QLD only.
SSL VPN Participants: None expected as DNS entry will be updated to remove QLD IP.
GASHUB: Nil
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point 202.44.78.10 for Policy Based VPN and 202.44.78.12 for Route Based VPN) prior to this scheduled outage.
*** Failure to do so will impact connectivity to Marketnet Services. ***
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0100719 | Production | Participant FTP File Server Maintenance
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: Participant FTP File Server Maintenance
Change Start Date & Time: 29/01/2025 10:00:00 AEST
Change End Date & Time: 29/01/2025 11:00:00 AEST
Outage Start Date & Time: 29/01/2025 10:15:00 AEST
Outage End Date & Time: 29/01/2025 10:15:30 AEST
Environment: Production
Participant Impact and Requirements: All external participants will be briefly disconnected (up to 30 seconds) and then automatically reconnected.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1800 hrs 24/01/2025 to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 854 MW.
The minimum capacity reserve available is 759 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Bundey to Buronga (6F) 330kV line - NSW region - 24/01/2025
Inter-regional transfer limit variation - Bundey to Buronga (6F) 330kV line - NSW region - 24/01/2025
A planned outage of Bundey to Buronga (6F) 330kV line in the NSW region was scheduled from 1931 hrs 21/01/2025 to 1900 hrs 25/01/2025.
The outage has been completed and Bundey to Buronga (6F) 330kV line returned to service at 0900 hrs 24/01/2025
Constraint set(s) revoked: I-BDBU_ONE
Manager NEM Real Time Operations
CHG0100766 | Completed | Production | Planned Maintenance to Brisbane ISE Server
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Planned Maintenance to Brisbane ISE Server
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 24/01/2025
The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 123637 is cancelled at 0445 hrs 24/01/2025
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the Qld Region on 24/01/2025
The Forecast LOR2 condition in the Qld region advised in AEMO Electricity Market Notice No. 123636 is cancelled at 2340 hrs 23/01/2025
Manager NEM Real Time Operations