124051RECLASSIFY CONTINGENCY03/02/2025 04:32:50 PM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 1615 hrs 03/02/2025 until further notice

Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
124050RECLASSIFY CONTINGENCY03/02/2025 04:26:39 PM

Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Duration: 03/02/2025 1615 hrs until further notice

Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
124049RESERVE NOTICE03/02/2025 04:19:18 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1630 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1795 MW.
The minimum capacity reserve available is 1191 MW.


Manager NEM Real Time Operations
     
124048RECLASSIFY CONTINGENCY03/02/2025 03:42:01 PM

Reclassification of a Non-Credible Contingency Event: Gordon - Chapel St No 1 220kV line and Gordon - Chapel St No 2 220kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Gordon - Chapel St No 1 220kV and Gordon - Chapel St No 2 220kV

Duration: 03/02/2025 15:41 until further notice

Constraint set(s) invoked:
F-T-CSGO Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Auto-generated on behalf of Manager NEM Real Time Operations
     
124042RESERVE NOTICE03/02/2025 01:56:10 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1900 hrs 03/02/2025 to 2000 hrs 03/02/2025.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 243 MW.

AEMO is seeking a market response.

Manager NEM Real Time Operations
     
124039RESERVE NOTICE03/02/2025 10:39:23 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 124025 is cancelled at 1015 hrs 03/02/2025.

Manager NEM Real Time Operations
     
124038RESERVE NOTICE03/02/2025 10:32:42 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 124034 has been updated to the following:

[1.] From 1930 hrs 03/02/2025 to 2000 hrs 03/02/2025.
The forecast capacity reserve requirement is 583 MW.
The minimum capacity reserve available is 516 MW.

Manager NEM Real Time Operations
     
124037RESERVE NOTICE03/02/2025 10:24:52 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124033 is cancelled at 1015 hrs 03/02/2025.

Manager NEM Real Time Operations
     
124036MARKET SYSTEMS03/02/2025 09:32:00 AM

CHG0100610 | Completed | Production | Planned Maintenance to Brisbane Internet Router

Change Number: CHG0100610

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Internet Access

Change Title: Planned Maintenance to Brisbane Internet Router

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.

     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm