Update - Vulnerable lines in TAS region
Update - Lightning vulnerable lines in TAS region
Refer to AEMO Electricity Market Notice 124044
At 1410 hrs 03/02/2025 the Farrell - Reece No.1 and No.2 220 kV lines lines tripped.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the Farrell - Reece No.1 and No.2 220 kV lines to be vulnerable with a category of probable due to lightning.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124176 is cancelled at 1444 hrs 05/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1330 hrs.
The Actual LOR1 condition is forecast to exist until 1430 hrs
The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1254 MW
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 124096
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 05/02/2025.
The direction update is issued at 1315 hrs 05/02/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1730 hrs 05/02/2025 to 1900 hrs 05/02/2025.
The forecast capacity reserve requirement is 1733 MW.
The minimum capacity reserve available is 1581 MW.
[2.] From 1730 hrs 06/02/2025 to 1900 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1212 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 05/02/2025 to 1900 hrs 05/02/2025.
The forecast capacity reserve requirement is 1754 MW.
The minimum capacity reserve available is 1560 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124146 is cancelled at 1014 hrs 05/02/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1500 hrs 05/02/2025 to 1530 hrs 05/02/2025.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1292 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124144 is cancelled at 0814 hrs 05/02/2025.
Manager NEM Real Time Operations