124416INTER-REGIONAL TRANSFER10/02/2025 10:09:20 AM

Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025

At 0945 hrs 10/02/2025 there was an unplanned outage of Ingleburn - Wallerawang (77) 330 kV line.

The following constraint set(s) invoked at 0955 hrs 10/02/2025
N-X_AVMA_SSWW

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124400RESERVE NOTICE09/02/2025 05:51:30 PM

Cancellation of Actual (LOR1) condition in the NSW region - 09/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 09/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124399 is cancelled at 1749 hrs 09/02/2025.

Manager NEM Real Time Operations
     
124399RESERVE NOTICE09/02/2025 04:44:17 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs

The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1171 MW

Manager NEM Real Time Operations
     
124349PRICES SUBJECT TO REVIEW08/02/2025 01:35:23 PM

[EventId:202502081340_review] Prices for interval 08-Feb-2025 13:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1335 hrs on 8 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124348PRICES SUBJECT TO REVIEW08/02/2025 01:30:16 PM

[EventId:202502081335_review] Prices for interval 08-Feb-2025 13:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124347PRICES SUBJECT TO REVIEW08/02/2025 01:25:20 PM

[EventId:202502081330_review] Prices for interval 08-Feb-2025 13:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1325 hrs on 8 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124346PRICES SUBJECT TO REVIEW08/02/2025 01:20:23 PM

[EventId:202502081325_review] Prices for interval 08-Feb-2025 13:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1320 hrs on 8 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124345PRICES SUBJECT TO REVIEW08/02/2025 01:15:18 PM

[EventId:202502081320_review] Prices for interval 08-Feb-2025 13:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 8 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124344PRICES SUBJECT TO REVIEW08/02/2025 01:10:20 PM

[EventId:202502081315_review] Prices for interval 08-Feb-2025 13:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 8 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     