Market Notices

123593RESERVE NOTICE22/01/2025 06:14:27 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1830 hrs 22/01/2025 to 1900 hrs 22/01/2025.
The forecast capacity reserve requirement is 456 MW.
The minimum capacity reserve available is 343 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
123591SETTLEMENTS RESIDUE22/01/2025 06:00:29 PM

[EventId:202501221800_NRM_NSW1_QLD1_started] NEGRES CONSTRAINT NRM_NSW1_QLD1 started operating from 22 January 2025 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 22 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to QLD - 22 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to QLD directional interconnector.

The negative residue constraint set NRM_NSW1_QLD1 commenced operating from 1800 hrs on 22 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123585SETTLEMENTS RESIDUE22/01/2025 04:45:15 PM

[EventId:202501221645_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 January 2025 16:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1645 hrs on 22 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1645 hrs on 22 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123576SETTLEMENTS RESIDUE22/01/2025 03:31:15 PM

[EventId:202501221530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 January 2025 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 22 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2025.

Refer to market notice: 123560

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 22 January 2025.

This is an AEMO autogenerated Market Notice.
     
123574SETTLEMENTS RESIDUE22/01/2025 02:30:21 PM

[EventId:202501221430_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 22 January 2025 14:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 22 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.

Refer to market notice: 123571

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1430 hrs on 22 January 2025.

This is an AEMO autogenerated Market Notice.
     
123571SETTLEMENTS RESIDUE22/01/2025 02:13:46 PM

[EventId:202501221405_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 22 January 2025 14:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 22 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1405 hrs on 22 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123563SETTLEMENTS RESIDUE22/01/2025 01:56:54 PM

[EventId:202501221355_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 22 January 2025 13:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1355 hrs on 22 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.

Refer to market notice: 123556

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1355 hrs on 22 January 2025.

This is an AEMO autogenerated Market Notice.
     
123560SETTLEMENTS RESIDUE22/01/2025 01:46:49 PM

[EventId:202501221345_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 January 2025 13:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1345 hrs on 22 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1345 hrs on 22 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123556SETTLEMENTS RESIDUE22/01/2025 01:30:34 PM

[EventId:202501221330_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 22 January 2025 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 22 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1330 hrs on 22 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     