124221RESERVE NOTICE05/02/2025 09:42:25 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124183 has been updated at 2133 hrs 05/02/2025 to the following:

From 1730 hrs 07/02/2025 to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 1108 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124190MARKET SYSTEMS05/02/2025 04:23:24 PM

CHG0100111 | Pre-Production | Pre-Prod eMDM February Maintenance Release

Change Number: CHG0100111

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MDM - Meter Data Management_PreProd

Change Title: Pre-Prod eMDM February Maintenance Release

Change Start Date & Time: 11/02/2025 13:00:00 AEST
Change End Date & Time: 11/02/2025 17:00:00 AEST
Outage Start Date & Time: 11/02/2025 13:00:00 AEST
Outage End Date & Time: 11/02/2025 15:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
124183RESERVE NOTICE05/02/2025 04:17:25 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124154 has been updated at 1500 hrs 05/02/2025 to the following:

From 1630 hrs to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1162 MW.
The minimum capacity reserve available is 842 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124180GENERAL NOTICE05/02/2025 03:16:32 PM

Update - Vulnerable lines in TAS region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in TAS region
Refer to AEMO Electricity Market Notice 124044
At 1410 hrs 03/02/2025 the Farrell - Reece No.1 and No.2 220 kV lines lines tripped.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the Farrell - Reece No.1 and No.2 220 kV lines to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
     
124154RESERVE NOTICE05/02/2025 01:04:37 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124150 has been updated at 1200 hrs 05/02/2025 to the following:

From 1730 hrs to 1830 hrs 07/02/2025.
The forecast capacity reserve requirement is 1063 MW.
The minimum capacity reserve available is 967 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124150RESERVE NOTICE05/02/2025 11:04:33 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124143 has been updated at 1000 hrs 05/02/2025 to the following:

From 1630 hrs to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1161 MW.
The minimum capacity reserve available is 883 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124149RESERVE NOTICE05/02/2025 10:58:02 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124147 is cancelled at 1000 hrs 05/02/2025.

No LOR2 condition is currently forecast in the SA region in the STPASA period.

AEMO Operations
     
124147RESERVE NOTICE05/02/2025 09:51:53 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1800 hrs to 2030 hrs 11/02/2025.
The forecast capacity reserve requirement is 222 MW.
The minimum capacity reserve available is 180 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124143RESERVE NOTICE05/02/2025 04:36:11 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124066 has been updated at 0423 hrs 05/02/2025 to the following:

[1.] From 1600 hrs 07/02/2025 to 1930 hrs 07/02/2025.
The forecast capacity reserve requirement is 1144 MW.
The minimum capacity reserve available is 678 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.