125835INTER-REGIONAL TRANSFER21/03/2025 06:07:23 PM

Inter-regional transfer limit variation - Canberra - Lower Tumut (07) 330 kV Line. - NSW region - 21/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Canberra - Lower Tumut (07) 330 kV Line - NSW region - 21/03/2025

At 1746 hrs 21/03/2025 there was an unplanned outage of Canberra - Lower Tumut (07) 330 kV Line.

The following constraint sets invoked at 1800 hrs 21/03/2025
N-CNLT_07
N-X_4+07_WG_CLOSE

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW-QLD1
VIC-NSW1
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125826INTER-REGIONAL TRANSFER21/03/2025 12:21:33 PM

Inter-regional transfer limit variation - Darlington Point - Balranald X5 220kV Line - NSW region - 21/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Darlington Point - Balranald X5 220kV Line - NSW region - 21/03/2025

A planned outage of Darlington Point - Balranald X5 220kV Line in the NSW region was scheduled from 0600 hrs 21/03/2025 to 1600 hrs 21/03/2025.

The outage has been completed and Darlington Point - Balranald X5 220kV Line returned to service at 1220 hrs 21/03/2025

Constraint set(s) revoked: N-BADP

Manager NEM Real Time Operations
     
125788INTER-REGIONAL TRANSFER19/03/2025 03:12:44 PM

Inter-regional transfer limit variation - Robertstown - Tungkillo 1 275 kV line - SA region - 19/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Robertstown - Tungkillo 1 275 kV line - SA region - 19/03/2025

At 1450 hrs 19/03/2025 there was a short notice outage of Robertstown - Tungkillo 1 275 kV line.

The following constraint set(s) invoked at 1455 hrs 19/03/2025
S-RBTU

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125721RESERVE NOTICE16/03/2025 07:14:22 PM

Cancellation of Actual (LOR1) condition in the NSW region - 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 16/03/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125715 is cancelled at 1915 hrs 16/03/2025.

Manager NEM Real Time Operations
     
125715RESERVE NOTICE16/03/2025 05:14:31 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/03/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The forecast capacity reserve requirement is 1684 MW.
The minimum capacity reserve available is 1242 MW.


Manager NEM Real Time Operations
     
125701POWER SYSTEM EVENTS16/03/2025 11:47:57 AM

Non-credible contingency event - QLD region - 16/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 16/03/2025

At 1131 hrs the H35 Strathmore 132 kV No 2 bus tripped. Whitsunday Solar farm and Hamilton Solar farm were disconnected.

AEMO did not instruct load shedding.


The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
125692RESERVE NOTICE15/03/2025 06:36:39 PM

Cancellation of Actual (LOR1) condition in the NSW region - 15/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 15/03/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125691 is cancelled at 1835 hrs 15/03/2025.

Manager NEM Real Time Operations
     
125691RESERVE NOTICE15/03/2025 05:42:35 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/03/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/03/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1642 MW
The minimum capacity reserve available is 1550 MW

Manager NEM Real Time Operations
     
125654RESERVE NOTICE14/03/2025 06:40:25 PM

Cancellation of Actual (LOR1) condition in the NSW region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 14/03/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125652 is cancelled at 1840 hrs 14/03/2025.

Manager NEM Real Time Operations
     