PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 03/02/2025 to 1930 hrs 03/02/2025.
The forecast capacity reserve requirement is 371 MW.
The minimum capacity reserve available is 251 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No.124021 is cancelled at 2345 hrs 02/02/2025.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 03/02/2025
The Forecast LOR2 condition in the VIC region advised in AEMO Electricity Market Notice No.124022 is cancelled at 2345 hrs 02/02/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 03/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 1830 hrs 03/02/2025 to 1900 hrs 03/02/2025.
The forecast capacity reserve requirement is 823 MW.
The minimum capacity reserve available is 801 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 03/02/2025 to 1930 hrs 03/02/2025.
The forecast capacity reserve requirement is 404 MW.
The minimum capacity reserve available is 333 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202501301835_review] Prices for interval 30-Jan-2025 18:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 30 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501301830_review] Prices for interval 30-Jan-2025 18:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 30 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501301825_review] Prices for interval 30-Jan-2025 18:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 30 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501301820_review] Prices for interval 30-Jan-2025 18:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 30 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.