Filter by category
Filter by Date
[EventId:202503152000_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 March 2025 20:00
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 15 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2025.
Refer to market notice: 125680
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2000 hrs on 15 March 2025.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region SA1 Saturday, 15 March 2025
NON-CONFORMANCE SA1 Region Saturday, 15 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LADBROK2
Duration: 15/03/2025 17:00 to 15/03/2025 17:05
Amount: -9 MW
Constraint: NC-S_LADBROK2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Saturday, 15 March 2025
NON-CONFORMANCE SA1 Region Saturday, 15 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LADBROK1
Duration: 15/03/2025 17:00 to 15/03/2025 17:05
Amount: -7 MW
Constraint: NC-S_LADBROK1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202503151635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 March 2025 16:35
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 15 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1635 hrs on 15 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202503141730_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 March 2025 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 14 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 March 2025.
Refer to market notice: 125646
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1730 hrs on 14 March 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202503141635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 March 2025 16:35
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 14 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1635 hrs on 14 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202503131830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 March 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 13 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 March 2025.
Refer to market notice: 125605
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 13 March 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202503131740_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 March 2025 17:40
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 13 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1740 hrs on 13 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Thursday, 13 March 2025
NON-CONFORMANCE NSW1 Region Thursday, 13 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: NEWENSF2
Duration: 13/03/2025 10:40 to 13/03/2025 13:40
Amount: 62 MW
Constraint: NC-N_NEWENSF2
Auto-generated on behalf of Manager NEM Real Time Operations