124472INTER-REGIONAL TRANSFER11/02/2025 06:00:41 PM

Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025

At 1750 hrs 11/02/2025 there was a short notice outage of Yass Overload Control Scheme.

The following constraint set(s) invoked at 1750 hrs: N-YSWG_SCHEME

This constraint set(s) contains equations with the following interconnectors on the LHS,
V-S-MNSP1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124469INTER-REGIONAL TRANSFER11/02/2025 03:59:36 PM

Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025

At 1538 hrs 11/02/2025 there was an unplanned outage of MLTS-SMTS No1 500 kV line CB at SYTS .

The following constraint set(s) invoked at 1600 hrs 11/02/2025
V-SY_CB

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124468INTER-REGIONAL TRANSFER11/02/2025 03:40:29 PM

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

Referring to Market Notice 124466.

The power system security condition in the SA region, requiring AEMO to invoke the automated constraint set CA_SYDS_56BD5936 has ended at 1520 hrs.

Constraint set revoked: CA_SYDS_56BD5936

Manager NEM Real Time Operations
     
124466INTER-REGIONAL TRANSFER11/02/2025 02:19:04 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked automated constraint set CA_SYDS_56BD5936 from 1410 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-SA

Manager NEM Real Time Operations
     
124464NON-CONFORMANCE11/02/2025 02:00:17 PM

NON-CONFORMANCE Region NSW1 Tuesday, 11 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 11 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 11/02/2025 13:55 to 11/02/2025 14:00
Amount: -11 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124436NON-CONFORMANCE10/02/2025 02:10:15 PM

NON-CONFORMANCE Region NSW1 Monday, 10 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 10 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GULLRWF2
Duration: 10/02/2025 11:15 to 10/02/2025 14:10
Amount: 13 MW
Constraint: NC-N_GULLRWF2

Auto-generated on behalf of Manager NEM Real Time Operations
     
124416INTER-REGIONAL TRANSFER10/02/2025 10:09:20 AM

Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025

At 0945 hrs 10/02/2025 there was an unplanned outage of Ingleburn - Wallerawang (77) 330 kV line.

The following constraint set(s) invoked at 0955 hrs 10/02/2025
N-X_AVMA_SSWW

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124339NON-CONFORMANCE08/02/2025 08:05:22 AM

NON-CONFORMANCE Region VIC1 Saturday, 8 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Saturday, 8 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LYA2
Duration: 08/02/2025 07:55 to 08/02/2025 08:05
Amount: -39 MW
Constraint: NC-V_LYA2

Auto-generated on behalf of Manager NEM Real Time Operations
     
124301POWER SYSTEM EVENTS07/02/2025 03:34:46 PM

Update - Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 23/01/2025

Refer AEMO Electricity Market Notice 123615

At 0240 hrs on the 23/01/2025 there was a trip and auto reclose of the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     