Market Notices

124232INTER-REGIONAL TRANSFER06/02/2025 08:25:29 AM

Inter-regional transfer limit variation - Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025

The outage has been completed and Collector - Marulan (4) 330 kV line returned to service at 0825 hrs 06/02/2025

Constraint set(s) revoked: N-CTMN_4_WG_CLOSE

Manager NEM Real Time Operations
     
124231NON-CONFORMANCE06/02/2025 04:31:43 AM

NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 6 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 06/02/2025 01:25 to 06/02/2025 04:30
Amount: -44 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
124229NON-CONFORMANCE06/02/2025 12:25:20 AM

NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 5 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 05/02/2025 23:15 to 06/02/2025 00:25
Amount: -20 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
124190MARKET SYSTEMS05/02/2025 04:23:24 PM

CHG0100111 | Pre-Production | Pre-Prod eMDM February Maintenance Release

Change Number: CHG0100111

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MDM - Meter Data Management_PreProd

Change Title: Pre-Prod eMDM February Maintenance Release

Change Start Date & Time: 11/02/2025 13:00:00 AEST
Change End Date & Time: 11/02/2025 17:00:00 AEST
Outage Start Date & Time: 11/02/2025 13:00:00 AEST
Outage End Date & Time: 11/02/2025 15:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
124181POWER SYSTEM EVENTS05/02/2025 03:22:35 PM

Update - Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 03/02/2025

Refer AEMO Electricity Market Notice 124044

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will cancel the reclassification of this event as a credible contingency event.

Manager NEM Real Time Operations
     
124125INTER-REGIONAL TRANSFER04/02/2025 05:20:29 PM

Inter-regional transfer limit variation - Collector WF to Marulan No. 4 330 kV Line - NSW region - 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector WF to Marulan No. 4 330 kV Line - NSW region - 04/02/2025

A planned outage of Collector WF to Marulan No. 4 330 kV Line in the NSW region was scheduled from 0600 hrs 02/02/2025 to 1600 hrs 19/02/2025.

The outage has been completed and Collector WF to Marulan No. 4 330 kV Line returned to service at 1710 hrs 04/02/2025

Constraint set(s) revoked: N-CTMN_4_WG_CLOSE

Manager NEM Real Time Operations
     
124117NON-CONFORMANCE04/02/2025 04:05:34 PM

NON-CONFORMANCE Region QLD1 Tuesday, 4 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 4 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 04/02/2025 15:50 to 04/02/2025 16:00
Amount: 35 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
     
124077MARKET SYSTEMS04/02/2025 02:17:21 PM

CHG0101137 | Completed | Production | Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Change Number: CHG0101137

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Local Area Network

Change Title: Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
124065NON-CONFORMANCE04/02/2025 12:15:15 PM

NON-CONFORMANCE Region NSW1 Tuesday, 4 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 4 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 04/02/2025 12:05 to 04/02/2025 12:15
Amount: -57 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X