118252INTER-REGIONAL TRANSFER12/09/2024 12:40:03 PM

Inter-regional transfer limit variation - Murraylink - SA region - 12/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Murraylink - SA region - 12/09/2024

A planned outage of Murraylink in the SA region was scheduled from 1030 hrs 12/09/2024 to 1630 hrs 12/09/2024.

The outage has been completed and Murraylink returned to service at 1235 hrs 12/09/2024

Constraint set(s) revoked: I-MURRAYLINK

Manager NEM Real Time Operations
     
118251INTER-REGIONAL TRANSFER12/09/2024 12:33:53 PM

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 12/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 12/09/2024


A planned outage of Armidale - Sapphire 8E 330 KV Line in the NSW region was scheduled from 1630 hrs 11/09/2024 to 0900 hrs 16/09/2024.

The outage has been rescheduled for 1630 hrs 11/09/2024 to 1330 hrs 13/09/2024.


Constraint sets invoked: N-ARSR_8E, N-TW_SVC, N-DM_SVC


This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118248SETTLEMENTS RESIDUE12/09/2024 11:30:31 AM

[EventId:202409121130_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 September 2024 11:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1130 hrs on 12 September 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Refer to market notice: 118247

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1130 hrs on 12 September 2024.

This is an AEMO autogenerated Market Notice.
     
118247SETTLEMENTS RESIDUE12/09/2024 10:35:23 AM

[EventId:202409121035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 September 2024 10:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 12 September 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 12 September 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
118242INTER-REGIONAL TRANSFER11/09/2024 04:15:47 PM

Inter-regional transfer limit variation - Armidale- Sapphire 8E 330kV line - NSW region - 11/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale- Sapphire 8E 330kV line - NSW region - 11/09/2024

At 1610 hrs 11/09/2024 there was a short notice outage of Armidale- Sapphire 8E 330kV line.

The following constraint set(s) invoked at 1610 hrs 11/09/2024
N-ARSR_8E

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118240MARKET INTERVENTION11/09/2024 04:03:35 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118225

TORRB3 TORRENS ISLAN at 0400 hrs 12/09/2024 to remain synchronised and follow dispatch targets.

This update is issued at 1600 hrs 11/09/2024 and is expected to stay in place until 0400 hrs 13/09/2024

Manager NEM Real Time Operations
     
118231MARKET INTERVENTION11/09/2024 01:14:20 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0400 hrs 12/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
118226GENERAL NOTICE10/09/2024 05:55:51 PM

Network Augmentation Commissioned - NSW Region - 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 10/09/2024

At 1750 hrs, the following equipment at Buronga 330 kV substation has been commissioned:

1) Buronga 330 kV A bus.
2) Buronga 330 kV B bus.
3) Buronga No 1 330 kV capacitor.
4) Buronga No 2 330 kV capacitor.
5) Buronga No 7 330/220 kV transformer.

Manager NEM Real Time Operations
     
118225MARKET INTERVENTION10/09/2024 05:05:05 PM

Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAND

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 10/09/2024

Refer to Market Notice 118223


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1700 hrs 10/09/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0800 hrs 11/09/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 12/09/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     