Market Notices

123965MARKET INTERVENTION31/01/2025 03:59:12 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123924

PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1600 hrs 01/02/2025.

The direction update is issued at 1600 hrs 31/01/2025.

Manager NEM Real Time Operations
     
123961MARKET SYSTEMS31/01/2025 02:09:43 PM

CHG0101137 | Production | Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Change Number: CHG0101137

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Local Area Network

Change Title: Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Change Start Date & Time: 04/02/2025 11:00:00 AEST
Change End Date & Time: 04/02/2025 15:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned maintenance:

IPWAN Participants - Nil

Lan-2-Lan VPN Participants (IPSEC) - Nil

B2B VPN - Nil

SSL VPN Participants: Nil

GASHUB: Nil

Other Impacts will have been communicated in advance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
123957NON-CONFORMANCE31/01/2025 11:31:33 AM

NON-CONFORMANCE Region NSW1 Friday, 31 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 31 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 31/01/2025 11:05 to 31/01/2025 11:30
Amount: -226 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123931INTER-REGIONAL TRANSFER30/01/2025 03:24:25 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 2 Leg of Directlink .

The following constraint set was invoked at 1525 hrs 30/01/2025

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
123925MARKET INTERVENTION30/01/2025 04:03:21 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123884

TORRB2 TORRENS ISLAN at 0030 hrs 27/01/2025 to Remain synchronized and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 01/02/2025.

The direction update is issued at 1600 hrs 30/01/2025.

Manager NEM Real Time Operations
     
123924MARKET INTERVENTION30/01/2025 03:57:02 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123885

PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronized and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 01/02/2025.

The direction update is issued at 1600 hrs 30/01/2025.

Manager NEM Real Time Operations
     
123917NON-CONFORMANCE30/01/2025 06:50:11 AM

NON-CONFORMANCE Region NSW1 Thursday, 30 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 30 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 30/01/2025 06:45 to 30/01/2025 06:50
Amount: -14 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123885MARKET INTERVENTION29/01/2025 03:28:51 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123811

PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 31/01/2025.

The direction update is issued at 1500 hrs 29/01/2025.

Manager NEM Real Time Operations
     
123884MARKET INTERVENTION29/01/2025 03:22:31 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123812

TORRB2 TORRENS ISLAN at 0030 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 31/01/2025.

The direction update is issued at 1500 hrs 29/01/2025.

Manager NEM Real Time Operations
     