125606RESERVE NOTICE13/03/2025 05:45:09 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/03/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/03/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1668 MW
The minimum capacity reserve available is 1530 MW

Manager NEM Real Time Operations
     
125596NON-CONFORMANCE13/03/2025 01:40:18 PM

NON-CONFORMANCE Region NSW1 Thursday, 13 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 13 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NEWENSF2
Duration: 13/03/2025 10:40 to 13/03/2025 13:40
Amount: 62 MW
Constraint: NC-N_NEWENSF2

Auto-generated on behalf of Manager NEM Real Time Operations
     
125595NON-CONFORMANCE13/03/2025 01:40:18 PM

NON-CONFORMANCE Region NSW1 Thursday, 13 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 13 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NEWENSF1
Duration: 13/03/2025 10:40 to 13/03/2025 13:40
Amount: 68 MW
Constraint: NC-N_NEWENSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125592NON-CONFORMANCE13/03/2025 07:00:17 AM

NON-CONFORMANCE Region QLD1 Thursday, 13 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 13 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 13/03/2025 06:55 to 13/03/2025 07:00
Amount: -67 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125575NON-CONFORMANCE12/03/2025 05:35:15 PM

NON-CONFORMANCE Region NSW1 Wednesday, 12 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 12 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 12/03/2025 17:30 to 12/03/2025 17:35
Amount: 16 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125560INTER-REGIONAL TRANSFER12/03/2025 02:20:15 PM

Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025

An unplanned outage of Directlink Cables 1 and 2 in the NSW region was scheduled to return to service at 1700 hrs 12/03/2025.

The outage has been completed and Directlink Cables 1 and 2 returned to service at 1350 hrs 12/03/2025

Constraint set(s) revoked: N-X_MBTE_3

Manager NEM Real Time Operations
     
125543INTER-REGIONAL TRANSFER12/03/2025 07:03:39 AM

Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025

At 0641 hrs 12/03/2025 there was an unplanned outage of Waterloo - Hummocks 132kV Line.

The following constraint set(s) invoked at 0650 hrs 12/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125524GENERAL NOTICE11/03/2025 01:51:14 PM

NEM Local Temperature Alerts for SA, VIC from 11 Mar 2025 to 15 Mar 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 14th Mar, 15th Mar

VIC
Latrobe Valley Ap (39+ Deg C): 15th Mar
Mildura Ap (39+ Deg C): 14th Mar, 15th Mar

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
125521NON-CONFORMANCE11/03/2025 11:55:21 AM

NON-CONFORMANCE Region NSW1 Tuesday, 11 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 11 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 11/03/2025 11:25 to 11/03/2025 11:55
Amount: -9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm