NON-CONFORMANCE Region SA1 Monday, 27 January 2025
NON-CONFORMANCE SA1 Region Monday, 27 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: HPR1
Duration: 27/01/2025 15:40 to 27/01/2025 15:45
Amount: 12 MW
Constraint: NC-S_HPR1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202501271520_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 January 2025 15:20
Issued by Australian Energy Market Operator Ltd at 1520 hrs on 27 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 January 2025.
Refer to market notice: 123759
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1520 hrs on 27 January 2025.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 27/01/2025
In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_BRIS_56A99246_1 from 1450 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
Manager NEM Real Time Operations
[EventId:202501271505_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 27 January 2025 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 27 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 27 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1505 hrs on 27 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501271330_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 January 2025 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 27 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1330 hrs on 27 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Monday, 27 January 2025
NON-CONFORMANCE QLD1 Region Monday, 27 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GSTONE5
Duration: 27/01/2025 08:35 to 27/01/2025 08:50
Amount: 25 MW
Constraint: NC-Q_GSTONE5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 25 January 2025
NON-CONFORMANCE QLD1 Region Saturday, 25 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YARANSF1
Duration: 25/01/2025 12:40 to 25/01/2025 13:10
Amount: 37 MW
Constraint: NC-Q_YARANSF1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202501241630_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 24 January 2025 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 24 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 January 2025.
Refer to market notice: 123670
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1630 hrs on 24 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501241410_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 January 2025 14:10
Issued by Australian Energy Market Operator Ltd at 1410 hrs on 24 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1410 hrs on 24 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.