Filter by category
Filter by Date
Inter-regional transfer limit variation - Canberra - Lower Tumut (07) 330 kV Line. - NSW region - 21/03/2025
Inter-regional transfer limit variation -Canberra - Lower Tumut (07) 330 kV Line - NSW region - 21/03/2025
At 1746 hrs 21/03/2025 there was an unplanned outage of Canberra - Lower Tumut (07) 330 kV Line.
The following constraint sets invoked at 1800 hrs 21/03/2025
N-CNLT_07
N-X_4+07_WG_CLOSE
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW-QLD1
VIC-NSW1
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 21 March 2025
NON-CONFORMANCE QLD1 Region Friday, 21 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 21/03/2025 17:40 to 21/03/2025 17:45
Amount: -55 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Darlington Point - Balranald X5 220kV Line - NSW region - 21/03/2025
Inter-regional transfer limit variation - Darlington Point - Balranald X5 220kV Line - NSW region - 21/03/2025
A planned outage of Darlington Point - Balranald X5 220kV Line in the NSW region was scheduled from 0600 hrs 21/03/2025 to 1600 hrs 21/03/2025.
The outage has been completed and Darlington Point - Balranald X5 220kV Line returned to service at 1220 hrs 21/03/2025
Constraint set(s) revoked: N-BADP
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Robertstown - Tungkillo 1 275 kV line - SA region - 19/03/2025
Inter-regional transfer limit variation - Robertstown - Tungkillo 1 275 kV line - SA region - 19/03/2025
At 1450 hrs 19/03/2025 there was a short notice outage of Robertstown - Tungkillo 1 275 kV line.
The following constraint set(s) invoked at 1455 hrs 19/03/2025
S-RBTU
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Tuesday, 18 March 2025
NON-CONFORMANCE SA1 Region Tuesday, 18 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BLYTHB1
Duration: 18/03/2025 17:50 to 18/03/2025 18:25
Amount: 201 MW
Constraint: NC-S_BLYTHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 17 March 2025
NON-CONFORMANCE QLD1 Region Monday, 17 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WARWSF1
Duration: 17/03/2025 12:05 to 17/03/2025 12:10
Amount: 16 MW
Constraint: NC-Q_WARWSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Sunday, 16 March 2025
NON-CONFORMANCE NSW1 Region Sunday, 16 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 16/03/2025 18:15 to 16/03/2025 18:20
Amount: -10 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 16/03/2025
Non-credible contingency event - QLD region - 16/03/2025
At 1131 hrs the H35 Strathmore 132 kV No 2 bus tripped. Whitsunday Solar farm and Hamilton Solar farm were disconnected.
AEMO did not instruct load shedding.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Saturday, 15 March 2025
NON-CONFORMANCE SA1 Region Saturday, 15 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LADBROK2
Duration: 15/03/2025 17:00 to 15/03/2025 17:05
Amount: -9 MW
Constraint: NC-S_LADBROK2
Auto-generated on behalf of Manager NEM Real Time Operations