124043POWER SYSTEM EVENTS03/02/2025 02:02:24 PM

Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 03/02/2025

At 1333 hrs the Farrell - Reece No.1 and No.2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
124042RESERVE NOTICE03/02/2025 01:56:10 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1900 hrs 03/02/2025 to 2000 hrs 03/02/2025.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 243 MW.

AEMO is seeking a market response.

Manager NEM Real Time Operations
     
124037RESERVE NOTICE03/02/2025 10:24:52 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124033 is cancelled at 1015 hrs 03/02/2025.

Manager NEM Real Time Operations
     
124033RESERVE NOTICE03/02/2025 04:48:24 AM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 1830 hrs 03/02/2025 to 1930 hrs 03/02/2025.
The forecast capacity reserve requirement is 371 MW.
The minimum capacity reserve available is 251 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
124029RESERVE NOTICE02/02/2025 11:50:37 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No.124021 is cancelled at 2345 hrs 02/02/2025.

Manager NEM Real Time Operations
     
124027RESERVE NOTICE02/02/2025 11:56:48 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the VIC region advised in AEMO Electricity Market Notice No.124022 is cancelled at 2345 hrs 02/02/2025.

Manager NEM Real Time Operations
     
124022RESERVE NOTICE02/02/2025 11:08:04 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:


[1.] From 1830 hrs 03/02/2025 to 1900 hrs 03/02/2025.
The forecast capacity reserve requirement is 823 MW.
The minimum capacity reserve available is 801 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
124021RESERVE NOTICE02/02/2025 10:51:15 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 1830 hrs 03/02/2025 to 1930 hrs 03/02/2025.
The forecast capacity reserve requirement is 404 MW.
The minimum capacity reserve available is 333 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
124020INTER-REGIONAL TRANSFER02/02/2025 10:38:53 PM

Update - Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.

The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA

The following constraint set(s) invoked at 2230 hrs 02/02/2025
V-KIAMAL_SC_220CB

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     