Cancellation of Actual (LOR1) condition in the NSW region - 01/03/2025
Cancellation of Actual (LOR1) condition in the NSW region - 01/03/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125159 is cancelled at 1842 hrs 01/03/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/03/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/03/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1354 MW
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 01/03/2025
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_56D513DF from 1430 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
VIC1-NSW1
Manager NEM Real Time Operations
Yass to Wagga control scheme change - removal system normal constraint equations in NSW managing 990, 991 and 970 132kV lines
Transgrid has advised AEMO of an update to the Yass overload trip scheme. The scheme is normally armed managing line flow on 990, 991, 970 132kV lines and it is now operating both directions of flow from Wagga to Yass.
Based on this advice, the following constraint equations will be removed from the NSW system normal constraint sets N-NIL and N-NIL_991, effective immediately.
N>>NIL_970_051
N>>NIL_990_051
N>>NIL_991_051
Ben Blake
AEMO Operations
Inter-regional transfer limit variation - BassLink Harmonic Filter - TAS region - 23/02/2025
Inter-regional transfer limit variation - BassLink Harmonic Filter - TAS region - 23/02/2025
At 0305 hrs 23/02/2025 there was an unplanned outage of BassLink Harmonic Filter.
The following constraint set(s) invoked at 0305 hrs 23/02/2025
T-BLGC_HF_43MVAR
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector Windfarm - Yass (3L) 330 kV line - NSW region - 22/02/2025
Inter-regional transfer limit variation - Collector Windfarm - Yass (3L) 330 kV line - NSW region - 22/02/2025
A planned outage of Collector Windfarm - Yass (3L) 330 kV line in the NSW region was scheduled from 0600 hrs 17/02/2025 to 1600 hrs 24/02/2025.
The outage has been completed and Collector Windfarm - Yass (3L) 330 kV line returned to service at 0746 hrs 22/02/2025
Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE
Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 21/02/2025
Update - Non-credible contingency event - NSW region - 21/02/2025
Refer AEMO Electricity Market Notice 124944
At 1030 hrs the Capital WF A and C 330kV Buses were returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 20/02/2025
Non-credible contingency event - NSW region - 20/02/2025
At 1619 hrs the Capital WF A and C 330kV Buses tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 19/02/2025
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 19/02/2025
A planned outage of South Morang - Dederang No.1 330kV line series capacitor in the VIC region was scheduled from 0449 hrs 04/02/2025 to 1700 hrs 31/03/2025.
The outage has been completed and South Morang - Dederang No.1 330kV line series capacitor returned to service at 1205 hrs 19/02/2025
Constraint set(s) revoked: V-SMSC
Manager NEM Real Time Operations