125713RECLASSIFY CONTINGENCY16/03/2025 02:32:37 PM

Reclassification of a Non-Credible Contingency Event: Gordon - Chapel St No 1 220kV line and Gordon - Chapel St No 2 220kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Gordon - Chapel St No 1 220kV and Gordon - Chapel St No 2 220kV

Duration: 16/03/2025 14:32 until further notice

Constraint set(s) invoked:
F-T-CSGO Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-CSGO_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
125712RECLASSIFY CONTINGENCY16/03/2025 02:32:36 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 16/03/2025 14:32 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
125711SETTLEMENTS RESIDUE16/03/2025 02:30:28 PM

[EventId:202503161430_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 March 2025 14:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 16 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 March 2025.

Refer to market notice: 125706

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1430 hrs on 16 March 2025.

This is an AEMO autogenerated Market Notice.
     
125707RESERVE NOTICE16/03/2025 02:17:04 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125699 is cancelled at 1415 hrs.

Manager NEM Real Time Operations
     
125706SETTLEMENTS RESIDUE16/03/2025 02:05:20 PM

[EventId:202503161405_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 March 2025 14:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 16 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1405 hrs on 16 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125705SETTLEMENTS RESIDUE16/03/2025 01:45:21 PM

[EventId:202503161345_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 March 2025 13:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1345 hrs on 16 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 March 2025.

Refer to market notice: 125703

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1345 hrs on 16 March 2025.

This is an AEMO autogenerated Market Notice.
     
125703SETTLEMENTS RESIDUE16/03/2025 01:05:25 PM

[EventId:202503161305_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 March 2025 13:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 16 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1305 hrs on 16 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125702RECLASSIFY CONTINGENCY16/03/2025 01:00:14 PM

Update - Non-credible contingency event - QLD region - 16/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 16/03/2025

Refer AEMO Electricity Market Notice 125701

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: QLD

Elements: H35 Strathmore No 2 132 kV bus
Duration: 1300 hrs 16/03/2025 until further notice
Constraint set(s) invoked: NIL

Manager NEM Real Time Operations
     
125699RESERVE NOTICE16/03/2025 10:53:43 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125697 has been updated at 1045 hrs to the following:

From 1700 hrs 16/03/2025 to 1830 hrs 16/03/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 656 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     