Inter-regional transfer limit variation - Darlington Point - Balranald X5 220kV Line - NSW region - 21/03/2025
Inter-regional transfer limit variation - Darlington Point - Balranald X5 220kV Line - NSW region - 21/03/2025
A planned outage of Darlington Point - Balranald X5 220kV Line in the NSW region was scheduled from 0600 hrs 21/03/2025 to 1600 hrs 21/03/2025.
The outage has been completed and Darlington Point - Balranald X5 220kV Line returned to service at 1220 hrs 21/03/2025
Constraint set(s) revoked: N-BADP
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Robertstown - Tungkillo 1 275 kV line - SA region - 19/03/2025
Inter-regional transfer limit variation - Robertstown - Tungkillo 1 275 kV line - SA region - 19/03/2025
At 1450 hrs 19/03/2025 there was a short notice outage of Robertstown - Tungkillo 1 275 kV line.
The following constraint set(s) invoked at 1455 hrs 19/03/2025
S-RBTU
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025
Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025
At 1647 hrs 14/03/2025 there was a short notice outage of Lennox Head - Suffolk Park 9G3 132 kV Line.
The following constraint set(s) invoked at 1700 hrs 14/03/2025
N-BAMB_132_OPEN
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025
Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025
At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Waterloo 132 kV line.
The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUWT
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025
Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025
At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Bungama 132 kV line.
The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUBG
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025
Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025
An unplanned outage of Directlink Cables 1 and 2 in the NSW region was scheduled to return to service at 1700 hrs 12/03/2025.
The outage has been completed and Directlink Cables 1 and 2 returned to service at 1350 hrs 12/03/2025
Constraint set(s) revoked: N-X_MBTE_3
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025
Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025
At 0641 hrs 12/03/2025 there was an unplanned outage of Waterloo - Hummocks 132kV Line.
The following constraint set(s) invoked at 0650 hrs 12/03/2025
S-HUWT
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025
Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025
At 0917 hrs 11/03/2025 there was an unplanned outage of Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line.
The following constraint set(s) invoked at 0925 hrs 11/03/2025
S-KNPW and S-PWSE.
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update - AEMO market notice 125439 was published in error: AP STARTED for ENERGY in SA1 at 09 March 2025 17:55
Refer market notice 125439 and 125440
AEMO confirms that market notice 125439 was published in error.
An ADMINISTERED PRICE PERIOD has NOT been triggered in SA1 region.
Manager NEM Real Time Operations