STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 123471 is cancelled at 1400 hrs 21/01/2025.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs to 1700 hrs 28/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1073 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
[1.] From 1500 hrs 24/01/2025 to 1530 hrs 24/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 350 MW.
[2.] From 1800 hrs 24/01/2025 to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 884 MW.
The minimum capacity reserve available is 856 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 15/01/2025
Cancellation of Actual (LOR1) condition in the NSW region - 15/01/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123323 is cancelled at 1715 hrs 15/01/2025.
Manager NEM Real Time Operations
[EventId:202501151700_review] Prices for interval 15-Jan-2025 17:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1655 hrs on 15 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 17:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501151655_review] Prices for interval 15-Jan-2025 16:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1650 hrs on 15 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/01/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/01/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1700 hrs
The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1222 MW
Manager NEM Real Time Operations
[EventId:202501151650_review] Prices for interval 15-Jan-2025 16:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501151645_review] Prices for interval 15-Jan-2025 16:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1640 hrs on 15 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.