Market Notices

111938RESERVE NOTICE02/12/2023 04:20:57 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1900 hrs 03/12/2023 to 1930 hrs 03/12/2023.
The forecast capacity reserve requirement is 1295 MW.
The minimum capacity reserve available is 1270 MW.


Manager NEM Real Time Operations
111937RESERVE NOTICE02/12/2023 03:47:27 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111929 is cancelled at 1545 hrs 02/12/2023.

Manager NEM Real Time Operations
111929RESERVE NOTICE02/12/2023 02:26:39 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111926 has been updated at 1430 hrs to the following:

[1.] From 1830 hrs 03/12/2023 to 1930 hrs 03/12/2023.
The forecast capacity reserve requirement is 1292 MW.
The minimum capacity reserve available is 1236 MW.


Manager NEM Real Time Operations
111928RESERVE NOTICE02/12/2023 02:19:42 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 02/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111925 is cancelled at 1420 hrs 02/12/2023.

Manager NEM Real Time Operations
111926RESERVE NOTICE02/12/2023 01:08:58 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

[1.] From 1800 hrs 03/12/2023 to 1930 hrs 03/12/2023.
The forecast capacity reserve requirement is 1292 MW.
The minimum capacity reserve available is 1176 MW.

[2.] From 2000 hrs 03/12/2023 to 2030 hrs 03/12/2023.
The forecast capacity reserve requirement is 1303 MW.
The minimum capacity reserve available is 1282 MW.


Manager NEM Real Time Operations
111925RESERVE NOTICE02/12/2023 01:05:59 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 02/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

From 1900 hrs 02/12/2023 to 1930 hrs 02/12/2023.

The forecast capacity reserve requirement is 1301 MW.
The minimum capacity reserve available is 1277 MW.



Manager NEM Real Time Operations
111906RESERVE NOTICE01/12/2023 05:20:48 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 02/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111898 is cancelled at 1720 hrs 01/12/2023.

Manager NEM Real Time Operations
111898RESERVE NOTICE01/12/2023 01:26:17 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 02/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1830 hrs 02/12/2023 to 1900 hrs 02/12/2023.
The forecast capacity reserve requirement is 1305 MW.
The minimum capacity reserve available is 1265 MW.


Manager NEM Real Time Operations
111896MARKET SYSTEMS01/12/2023 09:48:04 AM

CHG0082190 | Pre-Production | Pre-Prod MSATS Mertering Exemption Release #2

Change Number: CHG0082190
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS Mertering Exemption Release #2
Change Start Date & Time: 05/12/2023 12:00:00 AEST
Change End Date & Time: 06/12/2023 12:00:00 AEST
Outage Start Date & Time: 05/12/2023 12:00:00 AEST
Outage End Date & Time: 05/12/2023 16:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm