Market Notices

117240INTER-REGIONAL TRANSFER28/06/2024 02:20:05 PM

Inter-regional transfer limit variation - Liddell to Tomago 82 330kV Line - NSW region - 28/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Liddell to Tomago 82 330kV Line - NSW region - 28/06/2024

At 1407 hrs 28/06/2024 there was an unplanned outage of Liddell to Tomago 82 330kV Line.

The following constraint set invoked at 1415 hrs 28/06/2024
N-LDTM_82_OPEN

This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
117239INTER-REGIONAL TRANSFER28/06/2024 02:07:43 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/06/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_5590C0E2 from 1355hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
117200INTER-REGIONAL TRANSFER26/06/2024 02:36:10 PM

Inter-regional transfer limit variation - Heywood - South East No 2 275 kV Line - SA region - 26/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Heywood - South East No 2 275 kV Line SA region - 26/06/2024

A planned outage of Heywood - South East No 2 275 kV Line in the SA region was scheduled from 0815 hrs 26/06/2024 to 1930 hrs 26/06/2024.

The outage has been completed and Heywood - South East No 2 275 kV Line returned to service at 1410 hrs 26/06/2024

Constraint set(s) revoked:
I-HYSE
I-VS_050
I-VS+LKB_050

Manager NEM Real Time Operations
117133INTER-REGIONAL TRANSFER25/06/2024 10:28:52 AM

Inter-regional transfer limit variation -Hazelwood - South Morang No 1 500 kV Line - VIC region - 25/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hazelwood - South Morang No 1 500 kV Line - VIC region - 25/06/2024

A planned outage of Hazelwood - South Morang No 1 500 kV Line in the VIC region was scheduled from 0800 hrs 25/06/2024 to 1530 hrs 25/06/2024.

The outage has been completed and Hazelwood - South Morang No 1 500 kV Line returned to service at 1016 hrs 25/06/2024

Constraint set(s) revoked: V-HWSM

Manager NEM Real Time Operations
117078INTER-REGIONAL TRANSFER19/06/2024 05:27:58 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 1725 hrs 19/06/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
117053INTER-REGIONAL TRANSFER18/06/2024 03:19:21 PM

Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024

A planned outage of Collector Wind Farm to Yass 3L 330kV line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1500 hrs 08/07/2024.

The outage has been completed and Collector Wind Farm to Yass 3L 330kV line returned to service at 1515 hrs 18/06/2024

Constraint set revoked: N-CTYS_3L_WG_CLOSE

Manager NEM Real Time Operations
116907INTER-REGIONAL TRANSFER07/06/2024 07:56:38 AM

Inter-Regional Transfer limit variation - Outage Cancelled - Planned outage of Moorabool - Mortlake No.2 500 kV Line in Vic region on 7 June 2024.

AEMO ELECTRICITY MARKET NOTICE

The Moorabool - Mortlake No.2 500kV Line in Victoria (VIC) region was planned to be on an outage on 07/06/2024. This outage has been withdrawn by the TNSP.

Constraint sets associated with this outage have been revoked.
I-VS+LKB_050, I-VS_050, V-MLMO

These constraint sets contains equations with the following interconnectors on the LHS.
V-SA, VIC1-NSW1, T-V-MNSP1, V-S-MNSP1

Refer to the AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
116906INTER-REGIONAL TRANSFER07/06/2024 04:39:57 AM

Inter-regional transfer limit variation - Heywood - Tarrone No.1 500kV line - VIC region - 07/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood - Tarrone No.1 500kV line - VIC region - 07/06/2024

At 0406 hrs 07/06/2024 there was an unplanned outage of Heywood - Tarrone No.1 500kV line

The following constraint set(s) invoked at 0415 hrs 07/06/2024
V-HYTR

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1, T-V-MNSP1, V-S-MNSP1, V-SA, VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
116904INTER-REGIONAL TRANSFER06/06/2024 02:29:13 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink, with the No.2 Leg of Directlink previously out-of-service.

The following constraint set was invoked at 1425 hrs 06/06/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations