Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line
Duration: 05/02/2025 13:47 until further notice
Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502051320_review] Prices for interval 05-Feb-2025 13:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 05/02/2025 13:11 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502051315_review] Prices for interval 05-Feb-2025 13:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1310 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502051310_review] Prices for interval 05-Feb-2025 13:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502051305_review] Prices for interval 05-Feb-2025 13:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502051300_review] Prices for interval 05-Feb-2025 13:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502051255_review] Prices for interval 05-Feb-2025 12:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1250 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 12:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1730 hrs 05/02/2025 to 1900 hrs 05/02/2025.
The forecast capacity reserve requirement is 1733 MW.
The minimum capacity reserve available is 1581 MW.
[2.] From 1730 hrs 06/02/2025 to 1900 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1212 MW.
Manager NEM Real Time Operations