[EventId:202410290625_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 29 October 2024 06:25
Issued by Australian Energy Market Operator Ltd at 0625 hrs on 29 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 October 2024.
Refer to market notice: 119605
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 0625 hrs on 29 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410290130_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 29 October 2024 01:30
Issued by Australian Energy Market Operator Ltd at 0130 hrs on 29 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 0130 hrs on 29 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410281900_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 28 October 2024 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 28 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 28 October 2024.
Refer to market notice: 119600
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1900 hrs on 28 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410281800_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 28 October 2024 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 28 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 28 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1800 hrs on 28 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410281620_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 28 October 2024 16:20
Issued by Australian Energy Market Operator Ltd at 1620 hrs on 28 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 28 October 2024.
Refer to market notice: 119587
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1620 hrs on 28 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410281600_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 28 October 2024 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 28 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 28 October 2024.
Refer to market notice: 119576
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1600 hrs on 28 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410281530_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 28 October 2024 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 28 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 28 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1530 hrs on 28 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of Minimum System Load 1 (MSL1) in the VIC Region on 03/11/2024
Cancellation - MSL1- VIC Region at 1400 hrs 28/10/2024.
Refer to Market Notice 119497 for Forecast MSL1.
AEMO Operations
[EventId:202410281505_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 28 October 2024 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 28 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 28 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1505 hrs on 28 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.