Inter-Regional Transfer limit variation - Murraylink power transfer limit reduction due to high temperature.
Inter-Regional Transfer limit variation - Murraylink power transfer limit reduction due to high temperature.
Murraylink power transfer limit has been reduced based on APA advice, consistent with the high ambient temperatures in the vicinity of Murraylink (Berri and Redcliffe).
Constraint sets I-SVML_165 and I-VSML_165 invoked from 1640 hrs.
The constraint set contains equations with the following interconnector on the LHS:
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111973 is cancelled at 1820 hrs 03/12/2023.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:
[1.] From 1800 hrs 03/12/2023 to 1930 hrs 03/12/2023.
The forecast capacity reserve requirement is 1293 MW.
The minimum capacity reserve available is 1168 MW.
[2.] From 2130 hrs 03/12/2023 to 2200 hrs 03/12/2023.
The forecast capacity reserve requirement is 1308 MW.
The minimum capacity reserve available is 1298 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - H2 South Pine 275kV SVC - QLD region - 03/12/2023
Inter-regional transfer limit variation - H2 South Pine 275kV SVC - QLD region - 03/12/2023
At 1626 hrs 03/12/2023 there was an unplanned outage of H2 South Pine 275kV SVC.
The following constraint set(s) invoked at 1630 hrs 03/12/2023
Q-SP_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1 - QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 03/12/2023
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111962 is cancelled at 1530 hrs 03/12/2023.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1630 hrs 08/12/2023 to 1800 hrs 08/12/2023.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1303 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:
[1.] From 1830 hrs 03/12/2023 to 1900 hrs 03/12/2023.
The forecast capacity reserve requirement is 1290 MW.
The minimum capacity reserve available is 1287 MW.
[2.] From 2130 hrs 03/12/2023 to 2200 hrs 03/12/2023.
The forecast capacity reserve requirement is 1308 MW.
The minimum capacity reserve available is 1253 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111941 is cancelled at 1825 hrs 02/12/2023.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2023
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 111938 has been updated at 1700 hrs to the following:
[1.] From 1830 hrs 03/12/2023 to 2000 hrs 03/12/2023.
The forecast capacity reserve requirement is 1295 MW.
The minimum capacity reserve available is 1150 MW.
[2.] From 2130 hrs 03/12/2023 to 2200 hrs 03/12/2023.
The forecast capacity reserve requirement is 1306 MW.
The minimum capacity reserve available is 1278 MW.
Manager NEM Real Time Operations