118360NON-CONFORMANCE21/09/2024 07:20:17 PM

NON-CONFORMANCE Region NSW1 Saturday, 21 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 21 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 21/09/2024 15:00 to 21/09/2024 19:20
Amount: 7 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
118355NON-CONFORMANCE21/09/2024 11:35:22 AM

NON-CONFORMANCE Region QLD1 Saturday, 21 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 21 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOUSF1
Duration: 21/09/2024 10:55 to 21/09/2024 11:35
Amount: 81 MW
Constraint: NC-Q_MOUSF1

Auto-generated on behalf of Manager NEM Real Time Operations
118346NON-CONFORMANCE20/09/2024 06:25:11 PM

NON-CONFORMANCE Region QLD1 Friday, 20 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 20 September 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: WDBESSG1, WDBESSL1
Aggregate Dispatch Group: WDBESS_ADG1
Duration: 20/09/2024 18:10 to 20/09/2024 18:25
Amount: -63 MW
Constraint: NC-Q_WDBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
118343NON-CONFORMANCE20/09/2024 05:40:18 PM

NON-CONFORMANCE Region QLD1 Friday, 20 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 20 September 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: WDBESSG1, WDBESSL1
Aggregate Dispatch Group: WDBESS_ADG1
Duration: 20/09/2024 17:15 to 20/09/2024 17:40
Amount: -63 MW
Constraint: NC-Q_WDBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
118314NON-CONFORMANCE18/09/2024 12:50:20 PM

NON-CONFORMANCE Region SA1 Wednesday, 18 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 18 September 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 18/09/2024 11:20 to 18/09/2024 12:50
Amount: 21 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
118310NON-CONFORMANCE17/09/2024 03:00:15 PM

NON-CONFORMANCE Region SA1 Tuesday, 17 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 17 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MANNSF2
Duration: 17/09/2024 14:10 to 17/09/2024 15:00
Amount: 23 MW
Constraint: NC-S_MANNSF2

Auto-generated on behalf of Manager NEM Real Time Operations
118277RESERVE NOTICE15/09/2024 11:28:16 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 118276 is cancelled at 1125 hrs 15/09/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
118276RESERVE NOTICE14/09/2024 08:50:32 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17 Sep 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:

[1.] From 1800 hrs 17/09/2024 to 1930 hrs 17/09/2024.
The forecast capacity reserve requirement is 1228 MW.
The minimum capacity reserve available is 1095 MW.


AEMO is seeking a market response.


Manager NEM Real Time Operations
118257SETTLEMENTS RESIDUE12/09/2024 04:55:27 PM

[EventId:202409121655_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 September 2024 16:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1655 hrs on 12 September 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Refer to market notice: 118256

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1655 hrs on 12 September 2024.