Market Notices

120616INTER-REGIONAL TRANSFER18/11/2024 04:02:01 PM

Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024

At 1545 hrs 18/11/2024 there was an unplanned outage of Southpine - Rocklea 809 275 kV Line.

The following constraint set(s) invoked at 1545 hrs 18/11/2024
Q-RLSP_809

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
120601PRICES SUBJECT TO REVIEW18/11/2024 09:45:27 AM

[EventId:202411180950_review] Prices for interval 18-Nov-2024 09:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0945 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 09:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120600PRICES SUBJECT TO REVIEW18/11/2024 09:40:24 AM

[EventId:202411180945_review] Prices for interval 18-Nov-2024 09:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0940 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 09:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120599PRICES SUBJECT TO REVIEW18/11/2024 09:35:19 AM

[EventId:202411180940_review] Prices for interval 18-Nov-2024 09:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0935 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 09:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120598PRICES SUBJECT TO REVIEW18/11/2024 09:30:25 AM

[EventId:202411180935_review] Prices for interval 18-Nov-2024 09:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0930 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 09:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120597PRICES SUBJECT TO REVIEW18/11/2024 09:25:22 AM

[EventId:202411180930_review] Prices for interval 18-Nov-2024 09:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0925 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 09:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120596PRICES SUBJECT TO REVIEW18/11/2024 09:20:31 AM

[EventId:202411180925_review] Prices for interval 18-Nov-2024 09:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0920 hrs on 18 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 09:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120563PRICES SUBJECT TO REVIEW17/11/2024 04:10:15 PM

[EventId:202411171615_review] Prices for interval 17-Nov-2024 16:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1610 hrs on 17 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Nov-2024 16:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120562PRICES SUBJECT TO REVIEW17/11/2024 04:05:18 PM

[EventId:202411171610_review] Prices for interval 17-Nov-2024 16:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 17 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Nov-2024 16:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     