Filter by category
Filter by Date
[EventId:202412211300_review] Prices for interval 21-Dec-2024 13:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 21 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 13:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412211255_review] Prices for interval 21-Dec-2024 12:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1250 hrs on 21 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 12:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412211250_review] Prices for interval 21-Dec-2024 12:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1245 hrs on 21 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 12:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line
Duration: 21/12/2024 12:41 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412211245_review] Prices for interval 21-Dec-2024 12:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1240 hrs on 21 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 12:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412211240_review] Prices for interval 21-Dec-2024 12:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 21 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 12:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412211230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 21 December 2024 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 21 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 21 December 2024.
Refer to market notice: 122343
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 21 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412211235_review] Prices for interval 21-Dec-2024 12:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 21 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 12:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412210800_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 21 December 2024 08:00
Issued by Australian Energy Market Operator Ltd at 0800 hrs on 21 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 21 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0800 hrs on 21 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.