Market Notices

120033PRICES SUBJECT TO REVIEW06/11/2024 06:00:15 PM

[EventId:202411061805_review] Prices for interval 06-Nov-2024 18:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 18:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120032PRICES SUBJECT TO REVIEW06/11/2024 05:55:23 PM

[EventId:202411061800_review] Prices for interval 06-Nov-2024 18:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 18:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120031MARKET INTERVENTION06/11/2024 05:57:50 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 119875

Direction is cancelled from: 1800 hrs 06/11/2024

Manager NEM Real Time Operations
     
120024PRICES SUBJECT TO REVIEW06/11/2024 05:25:20 PM

[EventId:202411061730_review] Prices for interval 06-Nov-2024 17:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 17:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120023PRICES SUBJECT TO REVIEW06/11/2024 05:20:22 PM

[EventId:202411061725_review] Prices for interval 06-Nov-2024 17:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 17:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120022PRICES SUBJECT TO REVIEW06/11/2024 05:15:21 PM

[EventId:202411061720_review] Prices for interval 06-Nov-2024 17:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 17:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120021PRICES SUBJECT TO REVIEW06/11/2024 05:10:24 PM

[EventId:202411061715_review] Prices for interval 06-Nov-2024 17:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1710 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 17:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120020PRICES SUBJECT TO REVIEW06/11/2024 05:05:21 PM

[EventId:202411061710_review] Prices for interval 06-Nov-2024 17:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 17:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120019MARKET INTERVENTION06/11/2024 05:07:43 PM

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 119875


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS at 1655 hrs 06/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 1700 hrs 06/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1800 hrs 06/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm