Filter by category
Filter by Date
[EventId:202411041405_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 November 2024 14:05
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 4 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1405 hrs on 4 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Update for the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119851 has been updated at 1300 hrs to the following:
From 1700 hrs to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 281 MW.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0600 hrs on 06/11/2024.
AEMO Operations
STPASA - Update for the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119849 has been updated at 1300 hrs to the following:
1. From 1300 hrs to 1330 hrs 07/11/2024.
The forecast capacity reserve requirement is 1191 MW.
The minimum capacity reserve available is 963 MW.
2. From 1430 hrs to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 269 MW.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0600 hrs on 06/11/2024.
AEMO Operations
[EventId:202411041300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 04 November 2024 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 4 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 November 2024.
Refer to market notice: 119856
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 4 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411041135_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 November 2024 11:35
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 4 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1135 hrs on 4 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119842 has been updated at 0800 hrs to the following:
From 1700 hrs to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 118 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 06/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119842 has been updated at 0800 hrs to the following:
From 1800 hrs to 1900 hrs 06/11/2024.
The forecast capacity reserve requirement is 849 MW.
The minimum capacity reserve available is 565 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119843 has been updated at 0800 hrs to the following:
From 1330 hrs to 2000 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 113 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119843 has been updated at 0800 hrs to the following:
From 1700 hrs to 2000 hrs 06/11/2024.
The forecast capacity reserve requirement is 1393 MW.
The minimum capacity reserve available is 555 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations