Filter by category
Filter by Date
Non-credible contingency event - TAS region - 19/09/2024
Non-credible contingency event - TAS region - 19/09/2024
At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Planned outage of Tailem Bend - South East 275 kV transmission line in the South Australia region beginning on 20/09/2024
The Tailem Bend - South East No 1 275 kV line in the South Australian (SA) region is planned to be out of service from 2100 hrs on 20/09/2024 to 0530 hrs on 21/09/2024.
A credible contingency event during this planned outage could cause synchronous separation of the SA region from the rest of the NEM.
During this planned outage:
- Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
- Post contingent FCAS will be sourced within SA following Separation event.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/09/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 118276 is cancelled at 1125 hrs 15/09/2024.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17 Sep 2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:
[1.] From 1800 hrs 17/09/2024 to 1930 hrs 17/09/2024.
The forecast capacity reserve requirement is 1228 MW.
The minimum capacity reserve available is 1095 MW.
AEMO is seeking a market response.
Manager NEM Real Time Operations
[EventId:202409111325_review] Prices for interval 11-Sep-2024 13:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1320 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111320_review] Prices for interval 11-Sep-2024 13:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111315_review] Prices for interval 11-Sep-2024 13:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1310 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111310_review] Prices for interval 11-Sep-2024 13:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111305_review] Prices for interval 11-Sep-2024 13:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.