115195RECALL GEN CAPACITY27/02/2024 08:26:49 AM

Request for Generator Recall Information for 29/02/2024 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 115193.

Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
115178RESERVE NOTICE26/02/2024 07:48:34 PM

Cancellation of Actual (LOR1) condition in the QLD region - 26/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 26/02/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No. 115160 is cancelled at 1940 hrs 26/02/2024.

Manager NEM Real Time Operations
115160RESERVE NOTICE26/02/2024 05:43:39 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 26/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 26/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs

The capacity reserve requirement is 922 MW
The minimum capacity reserve available is 706 MW

Manager NEM Real Time Operations
115048RESERVE NOTICE23/02/2024 04:46:12 PM

Cancellation of Actual (LOR1) condition in the NSW region - 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 23/02/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.115047 is cancelled at 1645 hrs 23/02/2024.

Manager NEM Real Time Operations
115047RESERVE NOTICE23/02/2024 04:12:17 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 23/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1600 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1252 MW

Manager NEM Real Time Operations
114930RESERVE NOTICE21/02/2024 07:45:35 PM

Cancellation of Actual (LOR1) condition in the SA region - 21/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 21/02/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.114929 is cancelled at 1945 hrs 21/02/2024.

Manager NEM Real Time Operations
114929RESERVE NOTICE21/02/2024 07:22:43 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

Refer AEMO Electricity Market Notice 114927

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1900 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch

The capacity reserve requirement is 428 MW
The minimum capacity reserve available is 277 MW

Manager NEM Real Time Operations
114927RESERVE NOTICE21/02/2024 06:47:19 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch

The capacity reserve requirement is 431 MW
The minimum capacity reserve available is 414 MW

Manager NEM Real Time Operations
114718PRICE ADJUSTMENT14/02/2024 02:52:11 PM

[EventId:202402131320_confirmed] Prices for interval 13-Feb-2024 13:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1452 hrs on 14 February 2024

PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2024 13:20.

In accordance with Market Notice 114583 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
- Over-Constrained Dispatch has been resolved for dispatch interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 -$38.41 -$35.04
QLD1 -$40.60 -$36.57
LOWERREG
TAS1 $16,600.00 $9.88
RAISEREG
TAS1 $16,600.00 $150.68


This is an AEMO autogenerated Market Notice.