STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121734 has been updated at 0800 hrs 12/12/2024 to the following:
From 1500 hrs to 1930 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 733 MW at 1730 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1283 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1830 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1401 MW.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Basslink
Inter-Regional Transfer limit variation - Basslink
There has been an unplanned outage of the Basslink interconnector.
The following constraint set was invoked at 0130 hrs 12/12/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1530 hrs 16/12/2024 to 1600 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 10 MW at 1530 hrs.
[2.] From 1700 hrs 16/12/2024 to 1830 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 106 MW at 1730 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121693 is cancelled at 1400 hrs 11/12/2024.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121692 has been updated at 1400 hrs 11/12/2024 to the following:
1. From 1500 hrs to 1700 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1900 hrs to 2030 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
1. From 1630 hrs to 1900 hrs 13/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1336 MW.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 10/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121702 is cancelled at 1840 hrs 10/12/2024.
Manager NEM Real Time Operations