Market Notices

122377MINIMUM SYSTEM LOAD21/12/2024 04:15:17 PM

Forecast Minimum System Load MSL1 condition in the VIC Region on 22/12/2024

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the VIC Region on 22/12/2024

Update to Market Notice 122271 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 22/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1825 MW
- MSL2 - 1325 MW
- MSL3 - 825 MW

The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1030 hrs 22/12/2024 to 1430 hrs 22/12/2024. Minimum regional demand is forecast to be 1335 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

Manager NEM Real Time Operations
     
122373MARKET INTERVENTION21/12/2024 03:53:54 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122312

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 23/12/2024.

The direction update is issued at 1600 hrs 21/12/2024.

Manager NEM Real Time Operations
     
122372MARKET INTERVENTION21/12/2024 03:52:37 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122311

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 23/12/2024.

The direction update is issued at 1600 hrs 21/12/2024.

Manager NEM Real Time Operations
     
122369MINIMUM SYSTEM LOAD21/12/2024 02:45:39 PM

Forecast Minimum System Load MSL2 condition in the VIC Region on 22/12/2024

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL2 condition in the VIC Region on 22/12/2024

Update to Market Notice 122341 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 22/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1825 MW
- MSL2 - 1325 MW
- MSL3 - 825 MW

The regional demand is forecast to be below the MSL2 threshold for the following period[s]:
- From 1230 hrs 22/12/2024 to 1300 hrs 22/12/2024. Minimum regional demand is forecast to be 1314 MW at 1300 hrs.


Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO is seeking a market response.


Manager NEM Real Time Operations
     
122359PRICES SUBJECT TO REVIEW21/12/2024 01:10:17 PM

[EventId:202412211315_review] Prices for interval 21-Dec-2024 13:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 21 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 13:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122357PRICES SUBJECT TO REVIEW21/12/2024 01:05:17 PM

[EventId:202412211310_review] Prices for interval 21-Dec-2024 13:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 21 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 13:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122355PRICES SUBJECT TO REVIEW21/12/2024 01:01:47 PM

[EventId:202412211305_review] Prices for interval 21-Dec-2024 13:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 21 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 13:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122352PRICES SUBJECT TO REVIEW21/12/2024 12:55:21 PM

[EventId:202412211300_review] Prices for interval 21-Dec-2024 13:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1255 hrs on 21 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 13:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122351PRICES SUBJECT TO REVIEW21/12/2024 12:50:25 PM

[EventId:202412211255_review] Prices for interval 21-Dec-2024 12:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1250 hrs on 21 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 12:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm