STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/12/2023
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1630 hrs 08/12/2023 to 1730 hrs 08/12/2023.
The forecast capacity reserve requirement is 1417 MW.
The minimum capacity reserve available is 1376 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
CHG0082190 | Pre-Production | Pre-Prod MSATS Mertering Exemption Release #2
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS Mertering Exemption Release #2
Change Start Date & Time: 05/12/2023 12:00:00 AEST
Change End Date & Time: 06/12/2023 12:00:00 AEST
Outage Start Date & Time: 05/12/2023 12:00:00 AEST
Outage End Date & Time: 05/12/2023 16:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .