Filter by category
Filter by Date
[EventId:202405011730_review] Prices for interval 01-May-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 1 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-May-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405011725_review] Prices for interval 01-May-2024 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 1 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-May-2024 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405011720_review] Prices for interval 01-May-2024 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 1 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-May-2024 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405011715_review] Prices for interval 01-May-2024 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 1 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-May-2024 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405011710_review] Prices for interval 01-May-2024 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 1 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-May-2024 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Planned outage of Gordon - Chapel St No. 1 220 kV line in the TAS region on 26/04/2024
The Gordon - Chapel St No. 1 220 kV line in the Tasmania (TAS) region is planned to be out of service from 1030 hrs on 26/04/2024 to 1500 hrs on 26/04/2024
A credible contingency event during this planned outage could cause a large reduction in generation in TAS.
Refer AEMO Network Outage Schedule (NOS) for further details.
Manager NEM Real Time Operations
[EventId:202404241735_review] Prices for interval 24-Apr-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241730_review] Prices for interval 24-Apr-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241725_review] Prices for interval 24-Apr-2024 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.