Filter by category
Filter by Date
NON-CONFORMANCE Region VIC1 Sunday, 14 July 2024
NON-CONFORMANCE VIC1 Region Sunday, 14 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS1
Duration: 14/07/2024 01:40 to 14/07/2024 01:45
Amount: -35 MW
Constraint: NC-V_YWPS1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 12 July 2024
NON-CONFORMANCE QLD1 Region Friday, 12 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 12/07/2024 07:05 to 12/07/2024 07:55
Amount: -74 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 7 July 2024
NON-CONFORMANCE QLD1 Region Sunday, 7 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TARONG#3
Duration: 07/07/2024 09:05 to 07/07/2024 09:30
Amount: -16 MW
Constraint: NC-Q_TARONG#3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Saturday, 6 July 2024
NON-CONFORMANCE SA1 Region Saturday, 6 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BOWWPV1
Duration: 06/07/2024 13:20 to 06/07/2024 13:55
Amount: 6 MW
Constraint: NC-S_BOWWPV1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 6 July 2024
NON-CONFORMANCE QLD1 Region Saturday, 6 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 06/07/2024 04:00 to 06/07/2024 04:30
Amount: 33 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 3 July 2024
NON-CONFORMANCE QLD1 Region Wednesday, 3 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: CALL_B_1
Duration: 03/07/2024 21:55 to 03/07/2024 22:00
Amount: -97 MW
Constraint: NC-Q_CALL_B_1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117284 is cancelled at 2010 hrs 03/07/2024.
Manager NEM Real Time Operations
[EventId:202407031755_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 July 2024 17:55
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 3 July 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.
Refer to market notice: 117283
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1755 hrs on 3 July 2024.
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 766 MW
Manager NEM Real Time Operations