117032RESERVE NOTICE17/06/2024 03:28:09 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0000 hrs to 0030 hrs 21/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1677 MW.

AEMO Operations
117031RESERVE NOTICE17/06/2024 03:29:14 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117025 has been updated at 1400 hrs 17/06/2024 to the following:

1. From 0000 hrs to 0100 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1669 MW.

2. From 0600 hrs to 1000 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1651 MW.

3. From 1600 hrs to 2359 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1641 MW.

AEMO Operations
117030RESERVE NOTICE17/06/2024 03:27:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117024 has been updated at 1400 hrs 17/06/2024 to the following:

1. From 0600 hrs to 0900 hrs 19/06/2024.
The forecast capacity reserve requirement is 1692 MW.
The minimum capacity reserve available is 1565 MW.

2. From 1600 hrs to 2359 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1556 MW.

AEMO Operations
117029MARKET SYSTEMS17/06/2024 01:55:46 PM

CHG0089836 | Completed | Pre-Production | Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.

Change Number: CHG0089836
Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal
Service/Component: Gas Hub

Change Title: Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117027GENERAL NOTICE17/06/2024 10:59:14 AM

QNI Minor testing (Qld to NSW) 17th June 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 114742

There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1300 MW on Monday 17th June 2024 from 1200 to 1800hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
117025RESERVE NOTICE16/06/2024 02:44:09 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117019 has been updated at 1400 hrs 16/06/2024 to the following:

[2.] From 1600 hrs 19/06/2024 to 0030 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1535 MW.
.

Manager NEM Real Time Operations
117024RESERVE NOTICE16/06/2024 02:43:10 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117018 has been updated at 1400 hrs 16/06/2024 to the following:

[1.] From 0530 hrs 19/06/2024 to 0930 hrs 19/06/2024.
The forecast capacity reserve requirement is 1721 MW.
The minimum capacity reserve available is 1521 MW.

[2.] From 1600 hrs 19/06/2024 to 0030 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1535 MW.


Manager NEM Real Time Operations
117023RESERVE NOTICE16/06/2024 02:42:00 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117017 is cancelled at 1400 hrs 16/06/2024.

Manager NEM Real Time Operations
117022RESERVE NOTICE16/06/2024 02:29:40 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No 117008 and No 1170016 is cancelled at 1400 hrs 16/06/2024.