NON-CONFORMANCE Region QLD1 Sunday, 7 July 2024
NON-CONFORMANCE QLD1 Region Sunday, 7 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TARONG#3
Duration: 07/07/2024 09:05 to 07/07/2024 09:30
Amount: -16 MW
Constraint: NC-Q_TARONG#3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Saturday, 6 July 2024
NON-CONFORMANCE SA1 Region Saturday, 6 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BOWWPV1
Duration: 06/07/2024 13:20 to 06/07/2024 13:55
Amount: 6 MW
Constraint: NC-S_BOWWPV1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation -Murraylink - SA region - 06/07/2024
Inter-regional transfer limit variation -Murraylink - SA region - 06/07/2024
A planned outage of Murraylink in the SA region was scheduled from 0700 hrs 28/06/2024 to 1700 hrs 09/07/2024.
The outage has been completed and Murraylink returned to service at 1035 hrs 06/07/2024
Constraint set(s) revoked: I-MURRAYLINK
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 6 July 2024
NON-CONFORMANCE QLD1 Region Saturday, 6 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 06/07/2024 04:00 to 06/07/2024 04:30
Amount: 33 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines - NSW region - 04/07/2024
Inter-regional transfer limit variation - Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines - NSW region - 04/07/2024
A planned outage of Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines in the NSW region was scheduled from 0800 hrs 03/07/2024 to 1700 hrs 04/07/2024.
The outage has been completed and Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines returned to service at 1405 hrs 04/07/2024
Constraint set(s) revoked: N-BYCR_61_15M and N-CRGR_3H
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - NSW region - 04/07/2024
Inter-regional transfer limit variation - Lismore - Dunoon 9U7 132 kV line - NSW region - 04/07/2024
A planned outage of Lismore - Dunoon 9U7 132 kV line in the NSW region was scheduled from 0732 hrs 02/07/2024 to 1700 hrs 19/07/2024.
The outage has been completed and Lismore - Dunoon 9U7 132 kV line returned to service at 1105 hrs 04/07/2024
Constraint set(s) revoked: N-LSDU_9U6
This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 3 July 2024
NON-CONFORMANCE QLD1 Region Wednesday, 3 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: CALL_B_1
Duration: 03/07/2024 21:55 to 03/07/2024 22:00
Amount: -97 MW
Constraint: NC-Q_CALL_B_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 3 July 2024
NON-CONFORMANCE QLD1 Region Wednesday, 3 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-1
Duration: 03/07/2024 14:40 to 03/07/2024 14:50
Amount: -18 MW
Constraint: NC-Q_STAN-1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 2 July 2024
NON-CONFORMANCE NSW1 Region Tuesday, 2 July 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: BHBG1, BHBL1
Aggregate Dispatch Group: BHBESS_ADG1
Duration: 02/07/2024 18:30 to 02/07/2024 18:40
Amount: -10 MW
Constraint: NC-N_BHBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations