CHG0085821 | Pre-Production | Pre-Prod MSATS Lifecycle Maintenance
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS Lifecycle Maintenance
Change Start Date & Time: 29/02/2024 09:00:00 AEST
Change End Date & Time: 01/03/2024 17:00:00 AEST
Outage Start Date & Time: 29/02/2024 10:00:00 AEST
Outage End Date & Time: 29/02/2024 14:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115148 has been updated at 1615 hrs to the following:
[1.] From 1800 hrs 26/02/2024 to 1900 hrs 26/02/2024.
The forecast capacity reserve requirement is 1155 MW.
The minimum capacity reserve available is 827 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1800 hrs 26/02/2024 to 1900 hrs 26/02/2024.
The forecast capacity reserve requirement is 1124 MW.
The minimum capacity reserve available is 974 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115113 has been updated at 1400 hrs 26/02/2024 to the following:
1. From 1430 hrs to 1630 hrs 29/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 685 MW.
2. From 1930 hrs to 2130 hrs 29/02/2024.
The forecast capacity reserve requirement is 1735 MW.
The minimum capacity reserve available is 1050 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/02/2024
From 1700 hrs to 2030 hrs 29/02/2024.
The forecast capacity reserve requirement is 1259 MW.
The minimum capacity reserve available is 729 MW.
AEMO Operations
CHG0085807 | Completed | Pre-Production | MSATS - eMDM Pre-Production Maintenance AKS v1.27 upgrade
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: MSATS - eMDM Pre-Production Maintenance AKS v1.27 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0082690 | UPDATED | Production | MSATS NEM Reform Metering Exemptions and B2M r44 Schema Go-Live
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS NEM Reform Metering Exemptions and B2M r44 Schema Go-Live
Change Start Date & Time: 03/03/2024 09:00:00 AEST
Change End Date & Time: 03/03/2024 17:00:00 AEST
Outage Start Date & Time: 03/03/2024 10:00:00 AEST
Outage End Date & Time: 03/03/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115087 has been updated at 1430 hrs 25/02/2024 to the following:
[1.] From 1800 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 1255 MW.
The minimum capacity reserve available is 1152 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115086 has been updated at 1430 hrs 25/02/2024 to the following:
[1.] From 1500 hrs 29/02/2024 to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 1402 MW.
The minimum capacity reserve available is 725 MW.
Manager NEM Real Time Operations