Filter by category
Filter by Date
[EventId:202412251715_confirmed] Prices for interval 25-Dec-2024 17:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024
PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:15.
In accordance with Market Notice 122477 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412251710_confirmed] Prices for interval 25-Dec-2024 17:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024
PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:10.
In accordance with Market Notice 122476 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412251730_review] Prices for interval 25-Dec-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 25 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412251725_review] Prices for interval 25-Dec-2024 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 25 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412251720_review] Prices for interval 25-Dec-2024 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 25 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412251715_review] Prices for interval 25-Dec-2024 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 25 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412251710_review] Prices for interval 25-Dec-2024 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 25 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412251705_review] Prices for interval 25-Dec-2024 17:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 25 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV
Cancellation time: 25/12/2024 16:44
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 122471
Auto-generated on behalf of Manager NEM Real Time Operations